Botswana left P36.3 billion of its development budget unspent over 14 financial years, with half of that shortfall recorded in the past two years, official figures show.
The 2027/28 Budget Strategy Paper shows that government allocated P230.7 billion to development expenditure between 2012/13 and 2025/26 but spent P194.4 billion. The figures, reported by The Business Weekly & Review, point to a persistent failure to prepare and deliver projects, rather than a single difficult budget year.
A two-year collapse in project delivery
Development spending fell below budget in 11 of the 14 financial years, producing an overall execution rate of 84.3 percent. Performance then deteriorated sharply, with underspending of 38.5 percent in 2024/25 and 29.3 percent in 2025/26.
The combined P18.2 billion shortfall in those two years accounts for roughly half of the cumulative P36.3 billion left unspent. In 2025/26 alone, government spent P16.16 billion against a revised development budget of P22.85 billion, returning P6.69 billion.
That amount represented 63.4 percent of the P10.6 billion total expenditure underspend for the year. Capital projects therefore carried a disproportionate share of spending adjustments.
Overall government expenditure declined by P2.3 billion in 2025/26, with development expenditure accounting for P2.1 billion of the reduction. Recurrent expenditure remained elevated, and personnel emoluments and pensions absorbed 55.8 percent of government revenue.
Recurrent spending reached P70.1 billion, exceeding total revenue by approximately P649 million. That left fewer resources for roads, public facilities and other productive investment, while mineral and customs revenues remained exposed to external economic conditions.
Why projects enter the budget before they are ready
Naledi Madala, senior policy advisor at the Ministry of Finance, told the recent Bank Gaborone Insights & Impact Roundtable that some projects entered the budget before preparation, feasibility studies and bankability assessments had been completed.
“This has been happening for many years. We are returning such a significant part of the development budget,” she said.
“It is simply because we put something there that is nowhere ready to be executed.”
Madala said ministries continued to return unspent development funds. She called for greater care in selecting projects for Budget Speeches, particularly as Botswana seeks to demonstrate fiscal discipline to international credit rating agencies.
“We are very much aware that this Budget Speech will need to send a strong message to the credit rating agencies. We need to be absolutely sure that what we are putting on the Budget Speech is what is ready,” she said.
The Budget Strategy Paper identifies procurement and contracting delays, inadequate project readiness, limited implementation capacity and project-specific difficulties. Madala said the Botswana Economic Transformation Programme, around 40 percent of whose projects are major public-sector initiatives, should help replace a long wishlist with an executable investment pipeline.
Feasibility does not guarantee financing
Economist Keith Jefferis told the roundtable that project feasibility and project financing are often confused. A technically sound proposal can remain stalled unless government or private investors commit money under a credible financing plan.
“A project is not a project being executed until it is funded, till there is a financing plan, whether public, private or a combination,” he said.
Feasibility studies establish whether projects are technically, economically and financially viable. They do not automatically secure funding. For public projects without commercial viability, government must decide how much it will contribute and how the balance will be financed.
Projects seeking private investment must also demonstrate a credible investment and financing structure. This matters for infrastructure that exceeds the national budget’s capacity, including the proposed Trans-Kalahari Railway and schemes requiring private investors or foreign government partners.
The International Monetary Fund’s December 2025 assessment of Botswana’s public investment management system identified unclear project selection criteria, inconsistent appraisal methods and limited use of cost-benefit analysis. It also found that some projects began without sufficient feasibility studies or risk assessments.
The IMF cited weak links between national development planning and budget allocations, alongside poor coordination between ministries and implementing agencies. Projects can consequently appear in budgets without the institutional arrangements needed to deliver them.
The A1 highway shows the gap between announcement and delivery
Jefferis expects government to keep reviewing, amending and, in some cases, dropping projects as fiscal conditions and priorities change.
“I think we will continue to see projects being dropped or amended,” he said.
He pointed to the proposed dual carriageway upgrade of the A1 highway. The 2025 State of the Nation Address announced plans to upgrade the 640-kilometre road from Ramatlabama to Ramokgwebana through a public-private partnership.
A private concessionaire would design, finance, construct, operate and maintain the road, supported by toll revenue. Government said a bankable feasibility study would precede procurement. The study was due to begin in August 2025 and conclude by April 2026, with procurement targeted for September 2026.
The 2026 State of the Nation Address gave no update on either process. President Duma Boko instead announced P772.4 million for urgent maintenance on six sections of the A1 corridor.
Government promises tighter project selection
The 2027/28 Budget Strategy Paper proposes closer alignment between allocations and project preparedness, procurement timelines, implementation capacity and realistic spending schedules. Feasibility studies, detailed engineering designs and realistic cost estimates will form the core tests of readiness.
Frequently asked questions
How much development money went unspent?
Botswana left P36.3 billion unspent over 14 years. The P18.2 billion returned in 2024/25 and 2025/26 accounts for roughly half of that total.
What will government prioritise in the coming financial year?
Government says it will complete ongoing high-impact projects before starting new ones, disclose delayed spending, review weak projects and rescope or discontinue schemes that are no longer viable.